Working Intermittently to Upgrade Floors at Auraria Higher Education Center
We worked during school breaks for 2 years to upgrade mechanical room floors in multiple buildings on the Auraria Higher Education Campus (AHEC).
School may have been out for summer, but the work was on for General Industrial Flooring. This complicated multiphase project involved updating the floors of multiple mechanical penthouses across 7 buildings on the Auraria Higher Education Campus in Denver, CO
AHEC comprises three separate higher education institutions, The Community College of Denver, Metropolitan State University of Denver, and the University of Colorado Denver. We worked around the schools’ academic schedules and ongoing infrastructure upgrades to ensure that no students or construction timelines were impacted. The project spanned two years from start to finish.
The Project
General Industrial Flooring was hired to install new epoxy flooring and cove base in the mechanical penthouses of seven buildings on AHEC’s downtown Denver campus.
To the uninitiated, a mechanical penthouse is the top story of a building that is dedicated to mechanical and/or electronics equipment. They usually house heating, ventilation and air conditioning (HVAC) equipment. Because it’s located on the top floor of the building, in this case above student classrooms below, a failure in the flooring system could result in damaging water or chemical leaks into the floors below.
Our Flooring Choice
Epoxy flooring was the desired choice to provide a strong, waterproof membrane across the floor. Epoxy would provide long lasting protection of the concrete slabs, and create a safe, non-skid surface with added cleanability and chemical resistance.
The Install
We installed both a three and a four coat Sherwin Williams Industrial epoxy system in silver grey along with a 4” cove base. A small outdoor area also required coating, where we used a Sherwin Williams industrial urethane cement system for added durability and UV protection, considering it was outdoors and would be continuously exposed to the elements.
A Complicated Schedule
Coordinating with HVAC work
This was a complicated project because it was part of a campus-wide HVAC infrastructure replacement project. Some of the existing mechanical equipment remained while others were being upgraded. Our flooring installation process involved phasing and working around existing mechanical equipment, as well as prepping spaces for new equipment simultaneously. That meant working in a lot of tight spaces and coordinating with the general contractor on scheduling. As the HVAC and plumbing build out took place, each building needed to be completed within a certain timeline.
Student Safety Precautions
Adding to the phasing challenges was the issue that school remained in session. While the materials used didn’t pose any safety considerations, there is an odor associated with epoxy (as there is with interior paint, for example). Since we were coating the floors in the mechanical areas where the HVAC was present, certain coatings couldn’t be applied during classroom hours.
How We Handled It
To accommodate the needs of the Auraria Higher Education Campus, we worked with the contractor, GH Phipps, to schedule around school breaks – completing large portions of the project over school breaks in the summer, over Thanksgiving, and Christmas breaks.
Ongoing partnership
The final product we delivered provided both the aesthetics and performance the client and general contractor were seeking, so they were happy to work with us again. What began as a single project led to a second associated project (now complete) and will likely lead to additional mechanical penthouse coatings in the future.
Experts in Tight Spaces and Tight Schedules
If you’re in the market for new floor coatings for mechanical rooms in the Denver area, give us a call. We have the knowledge to select the right coatings that will perform the way they need to in a challenging space. We also have extensive experience working around equipment and tight spaces, and working with our clients’ schedules to deliver a smooth experience.